[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146281":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1146281,801,1,"单选题","关于爆破作业管理要求，说法不正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","爆破作业单位应在施工前2天发布施工公告",true,{"key":16,"text":17,"correct":18},"B","爆破作业单位应爆破前1天发布爆破公告",false,{"key":20,"text":21,"correct":18},"C","爆破公告内容应有警戒标志、起爆信号",{"key":23,"text":24,"correct":18},"D","施工公告内容应有施工单位、爆破作业时限","爆破作业单位应在施工前3天发布施工公告，故A错误。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]