[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146270":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1146270,801,1,"单选题","在巷道掘进循环中占时最多的工序是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","永久支护",false,{"key":16,"text":17,"correct":14},"B","钻眼爆破",{"key":19,"text":20,"correct":14},"C","安全检查",{"key":22,"text":23,"correct":24},"D","装渣运渣",true,"巷道施工的装载与运输是掘进中劳动量大，占循环时间最长的工序，一般情况下它可占掘进循环时间的35%∽50%。故选D。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]