[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146256":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1146256,801,1,"单选题","影响立井基岩爆破炮眼深度的因素，包括有（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","炸药的消耗量",false,{"key":16,"text":17,"correct":18},"B","钻眼机具和作业方式",true,{"key":20,"text":21,"correct":14},"C","井筒断面大小",{"key":23,"text":24,"correct":14},"D","光面爆破方法","采用人工手持式风动凿岩机打眼深度1.5∽2.0m，伞形钻架钻眼深度3.0∽5.0m；短段掘砌混合作业时炮眼深度宜为3.5∽5.0m，单行作业或平行作业的炮眼深度可为2.0∽4.5m或更深，浅眼多循环作业的炮眼深度应为1.2∽2.0m。故应选B。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]