[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146205":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1146205,801,1,"单选题","关于矿区测量控制网的说法，不正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","这将矿区的整个测量系统纳入统一的平面坐标系统和高程系统之中",false,{"key":16,"text":17,"correct":14},"B","矿区地面首平面控制网必须考虑矿区远景发展规划",{"key":19,"text":20,"correct":21},"C","矿区地面高程首级控制网的布置范围和等级的选择，应由矿区面积确定，且宜布设成环形网",true,{"key":23,"text":24,"correct":14},"D","近井点和高程基点是矿山测量的基准点","矿区地面高程首级控制网的布设范围和等级选择，应由矿区长度确定，且宜布设成环形网。故C 不正确。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]