[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146198":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1146198,801,1,"单选题","关于施工测量的原则，说法不正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","由整体到局部",false,{"key":16,"text":17,"correct":14},"B","先控制后细部",{"key":19,"text":20,"correct":14},"C","由高级到低级",{"key":22,"text":23,"correct":24},"D","由细部到整体",true,"施工测量程序上应符合“由整体到局部”的要求，步骤上就非常好是“先控制后细部”，精度上应满足“由高级到低级”的要求。故D 不正确。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]