[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146186":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1146186,801,1,"单选题","基坑回填应由场地最低部分开始，自下而上分层铺填，分层夯实，采用人工填土时，每层虚铺的厚度可以为（）cm。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","20",true,{"key":16,"text":17,"correct":18},"B","40",false,{"key":20,"text":21,"correct":18},"C","60",{"key":23,"text":24,"correct":18},"D","80","人工填土每层虚铺厚度约20∽30cm，机械填土可为30∽50cm。故选A。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]