[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146154":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1146154,801,1,"单选题","地面建筑防水层质量检验的蓄水试验时间，一般为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1～2d",true,{"key":16,"text":17,"correct":18},"B","3d",false,{"key":20,"text":21,"correct":18},"C","半天",{"key":23,"text":24,"correct":18},"D","5h","防水层完工后，经蓄水试验无渗漏，方可铺设面层。蓄水高度不超过200mm，蓄水时间为24∽48h。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]