[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146066":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1146066,801,1,"单选题","矿业工程项目的风险性主要体现在（??）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工期长",false,{"key":16,"text":17,"correct":14},"B","条件难",{"key":19,"text":20,"correct":14},"C","项目效益低",{"key":22,"text":23,"correct":24},"D","多项条件的不确定",true,"风险就是一种不确定性的存在，项目的风险也就是这种不确定性以及不确定因素繁多所造成的。工期长的本身不是风险，而工期长所引起的一系列不确定因素，如政策稳定性、利率变动、社会条件等才是风险影响的因素；条件难易、项目效益高低如不存在变动，则其问题的性质就不是风险，只有这些因素存在不确定性，才对矿业项目产生风险影响。因此本题答案应为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]