[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1146016":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1146016,801,1,"单选题","在施工单位预验合格的基础上，组织正式竣工验收的是（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工单位",false,{"key":16,"text":17,"correct":14},"B","监理单位",{"key":19,"text":20,"correct":21},"C","建设单位",true,{"key":23,"text":24,"correct":14},"D","质检单位","单位工程完工后，经预验合格后，最终向建设单位提交竣工报告，建设单位收到竣工报告后，由建设单位组织施工(含分包单位)、设计、监理等单位(项目)负责人进行竣工验收。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]