[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145996":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1145996,801,1,"单选题","在进度计划受影响时，措施不合理的是（??）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","调配人员和设备力量",false,{"key":16,"text":17,"correct":14},"B","建设或监理单位协调",{"key":19,"text":20,"correct":14},"C","采取一定经济措施",{"key":22,"text":23,"correct":24},"D","施工单位削减设计内容",true,"在项目的实施过程中，进度计划一旦发生延误或影响，应及时采取相关措施，通常可采用的措施包括有组织措施、技术措施、经济措施和管理措施等。采取调配人员和施工设备力量，属于组织措施和技术措施；由建设或监理单位协调属于管理措施；采取一定的经济措施属于经济措施；施工单位削减设计内容是不合理的，只有建设单位才有权利进行设计内容的变更。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]