[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145988":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1145988,801,1,"单选题","通常，不会影响矿井建设工期的井巷工程项目是（??）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","立井井筒",false,{"key":16,"text":17,"correct":14},"B","主要运输大巷",{"key":19,"text":20,"correct":21},"C","井底煤仓",true,{"key":23,"text":24,"correct":14},"D","风井总回风巷","在矿山井巷工程中，部分前后连贯的工程构成了全矿井施工需时最长的工程，这就形成了关键路线。通常这些项目是：井筒→井底车场重车线→主要石门→运输大巷→采区车场→采区上山→最后一个采区切割巷道或与风井贯通巷道等。井巷工程关键路线决定着矿井的建设工期。由于井底煤仓不是构成关键路线的工程项目，因此不会影响矿井建设工期。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]