[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145986":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1145986,801,1,"单选题","矿山工程的建井工期是（??）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","准备期与矿井竣工期之和",false,{"key":16,"text":17,"correct":14},"B","建井总工期",{"key":19,"text":20,"correct":14},"C","矿井投产期",{"key":22,"text":23,"correct":24},"D","竣工期",true,"矿井从完成建设用地的征购工作，施工人员进场，开始场内施工准备工作之日起，至项目正式开工为止叫施工准备期。矿井从项目正式开工(矿井以关键路线上任何一个井筒破土动工)之日起到部分工作面建成，并经试运转，试生产后正式投产所经历的时间，为矿井投产工期。矿井从项目正式开工之日起到按照设计规定完成建设工程，并经过试生产，试运转后正式竣工、交付生产所经历的时间为矿井竣工工期，也称建井工期。",{"id":6,"name":27,"category":28,"favorite":29},"一建矿业工程实务","建筑工程",0]