[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145763":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1145763,800,1,"单选题","关于合同评审的说法，错误的是（ ）。（2013 年真题）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","合同评审应在合同签订后进行",true,{"key":16,"text":17,"correct":18},"B","合同评审包括合同风险评估",false,{"key":20,"text":21,"correct":18},"C","应评审招标文件的完备性",{"key":23,"text":24,"correct":18},"D","合同发生重大变故后评审","承包人的合同管理应遵循下列程序：合同评审；合同订立；合同实施计划；合同实施控制；合同综合评价；有关知识产权的合法使用。可见A 选项说法错误。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]