[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145755":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1145755,800,2,"多选题","下列分部分项工程中，其专项施工方案必须进行专家论证的有（ ）。（2014 年真题）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","架体高度23m 的悬挑脚手架",true,{"key":16,"text":17,"correct":18},"B","开挖深度10m 的人工挖孔桩",false,{"key":20,"text":21,"correct":14},"C","爬升高度80m 的爬模",{"key":23,"text":24,"correct":14},"D","埋深10m 的地下暗挖",{"key":26,"text":27,"correct":14},"E","开挖深度5m 的无支护土方开挖工程","ACDE","专项施工方案必须进行专家论证的有：（1）架体高度20m 及以上悬挑式脚手架工程；（2）开挖深度超过16m 的人工挖孔桩工程；（3）工具式模板工程，包括滑模、爬模、飞模工程；（4）开挖深度超过5m（含5m）的基坑（槽）的土方开挖、支护、降水工程；（5）地下暗挖工程、顶管工程、水下作业工程。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]