[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145747":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1145747,800,1,"单选题","工程竣工验收合格之日起最多（ ）日内，建设单位应向当地建设行政主管部门备案。（2013年）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":18},"B","15",true,{"key":20,"text":21,"correct":14},"C","30",{"key":23,"text":24,"correct":14},"D","90","《建设工程质量管理条例》第四十九条规定：建设单位应当自建设工程竣工验收合格之日起15 日内，将建设工程竣工验收报告和规划、公安消防、环保等部门出具的认可文件或者准许使用文件报建设行政主管部门或者其他有关部门备案。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]