[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145732":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1145732,800,1,"单选题","某工程每月所需混凝土量相同，混凝土用量为3200m3，计划4个月完成，混凝土综合价格为1000元\u002Fm3；实际混凝土用量为5000m3，用时5个月，从第1个月至第5个月各月混凝土价格指数(%)为100,115，110，105，115。则根据赢得值法，前3个月的费用偏差为()万元。( 2015年真题)",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","-30",false,{"key":16,"text":17,"correct":18},"B","-25",true,{"key":20,"text":21,"correct":14},"C","-22",{"key":23,"text":24,"correct":14},"D","-20","本题考查的是赢得值法。费用偏差=已完工作预算费用-已完工作实际费用=(1000×1000×3)-(1000×100%×1000+1000×115%×1000+1000×110%×1000)=-250000元。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]