[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145730":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1145730,800,1,"单选题","应用曲线法进行施工成本偏差分析时，已完工作实际成本曲线与已完工作预算成本曲线的竖向距离，表示（）。( 2012年真题)",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本偏差",true,{"key":16,"text":17,"correct":18},"B","进度偏差",false,{"key":20,"text":21,"correct":18},"C","进度局部偏差",{"key":23,"text":24,"correct":18},"D","成本局部偏差","曲线图中，已完工作实际成本曲线与已完工作预算成本曲线的竖向距离是成本偏差，即成本偏差=已完工作预算成本-已完工作实际成本。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]