[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145726":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1145726,800,1,"单选题","成本偏差的控制的各工作步骤中，其核心是（）。( 2012年真题)",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","比较",false,{"key":16,"text":17,"correct":14},"B","预测",{"key":19,"text":20,"correct":21},"C","纠偏",true,{"key":23,"text":24,"correct":14},"D","分析","成本偏差的控制，分析是关键，纠偏是核心；要针对分析得出的偏差发生原因，采取切实措施，加以纠正",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]