[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145711":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1145711,800,2,"多选题","关于后张预应力混凝土模板拆除的说法，正确的有（ ）。（2013 年真题）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","梁侧模应在预应力张拉前拆除",true,{"key":16,"text":17,"correct":18},"B","梁侧模应在预应力张拉后拆除",false,{"key":20,"text":21,"correct":14},"C","混凝土强度达到侧模拆除条件即可拆除测模",{"key":23,"text":24,"correct":18},"D","梁底模应在预应力张拉前拆除",{"key":26,"text":27,"correct":14},"E","梁底模应在预应力张拉后拆除","ACE","后张预应力混凝土结构或构件模板的拆除，侧模应在预应力张拉前拆除，其混凝土强度达到侧模拆除条件即可。进行预应力张拉，必须在混凝土强度达到设计规定值时进行，底模必须在预应力张拉完毕方能拆除。@##",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]