[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145691":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1145691,800,1,"单选题","下列流水施工的基本组织形式中，其专业工作队数大于施工过程数的是（ ）。（2014 年真题）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","等节奏流水施工",false,{"key":16,"text":17,"correct":14},"B","异步距异节奏流水施工",{"key":19,"text":20,"correct":21},"C","等步距异节奏流水施工",true,{"key":23,"text":24,"correct":14},"D","无节奏流水施工","专业工作队数大于施工过程数，是等步距异节奏流水施工特点之一。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]