[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145659":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1145659,800,2,"多选题","混凝土在高温施工环境下施工，可采取的措施有（ ）。（2016 年真题）",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","在早间施工",true,{"key":16,"text":17,"correct":14},"B","在晚间施工",{"key":19,"text":20,"correct":14},"C","喷雾",{"key":22,"text":23,"correct":14},"D","连续浇筑",{"key":25,"text":26,"correct":27},"E","吹风",false,"ABCD","高温施工但并未提及选项中的施工措施。本题选项内容在二建《建筑》有给出，当日平均气温达到30℃及以上时，应按高温施工要求采取措施。混凝土浇筑宜在早间或晚间进行，且宜连续浇筑。当水分蒸发速率大于lkg\u002F（m2·h）时，应在施工作业面采取挡风、遮阳、喷雾等措施。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]