[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145649":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1145649,800,1,"单选题","肋梁楼盖无黏结预应力筋的张拉顺序：设计无要求时，通常是（ ）。2011年",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先张拉楼板，后张拉楼面梁",true,{"key":16,"text":17,"correct":18},"B","板中的无黏结筋须集中张拉",false,{"key":20,"text":21,"correct":18},"C","粱中的无黏结筋须同时张拉",{"key":23,"text":24,"correct":18},"D","先张拉楼面梁，后张拉楼板","无粘结预应力筋的张拉应严格按设计要求进行。通常，在预应力混凝土楼盖中的张拉顺序是先张拉楼板、后张拉楼面梁。板中的无粘结筋可依次张拉，梁中的无粘结筋可对称张拉 。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]