[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145627":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1145627,800,1,"单选题","受力钢筋代换应征得（ ）同意。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","监理单位",false,{"key":16,"text":17,"correct":14},"B","施工单位",{"key":19,"text":20,"correct":21},"C","设计单位",true,{"key":23,"text":24,"correct":14},"D","勘察单位","本题考查的是钢筋工程。钢筋的代换应征得设计单位的同意，相应费用按有关合同规定（一般应征得业主同意）并办理相应手续。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]