[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145618":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1145618,800,1,"单选题","下列暗龙骨吊顶工序的排序中，正确的是（ ）。（2016 年真题） ①安装主龙骨②安装副龙骨③安装水电管线④安装压条⑤安装罩面板",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","①③②④⑤",false,{"key":16,"text":17,"correct":14},"B","①②③④⑤",{"key":19,"text":20,"correct":21},"C","③①②⑤④",true,{"key":23,"text":24,"correct":14},"D","③②①④⑤","暗龙骨吊顶施工流程：放线→画龙骨分档线→安装水电管线→安装主龙骨→安装副龙骨→安装罩面板→安装压条。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]