[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145603":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1145603,800,2,"多选题","关于钢筋代换的说法，正确的有（ ）。2011年",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","当构件配筋受强度控制时，按钢筋代换前后强度相等的原则代换",true,{"key":16,"text":17,"correct":14},"B","当构件按最小配筋率配筋时，按钢筋代换前后截面面积相等的原则代换",{"key":19,"text":20,"correct":14},"C","钢筋代换应征得设计单位的同意",{"key":22,"text":23,"correct":14},"D","当构件受裂缝宽度控制时，代换前后应进行裂缝宽度和挠度验算",{"key":25,"text":26,"correct":27},"E","同钢号之间的代换按钢筋代换前后用钢量相等的原则代换",false,"ABCD","钢筋代换 1.代换原则：等强度代换或等面积代换。当构件配筋受强度控制时，按钢筋代换前后强度相等的原则进行代换；当构件按最小配筋率配筋时，或同钢号钢筋之间的代换，按钢筋代换前后面积相等的原则进行代换。当构件受裂缝宽度或挠度控制时，代换前后应进行裂缝宽度和挠度验算。 2.钢筋代换时，应征得设计单位的同意。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]