[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145597":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1145597,800,2,"多选题","关于钢筋混凝土预制桩锤击沉桩顺序的说法，正确的有（ ）。（2015 年真题）",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","基坑不大时，打桩可逐排打设",true,{"key":16,"text":17,"correct":14},"B","对于密集桩群，从中间开始分头向四周或两边对称施打",{"key":19,"text":20,"correct":14},"C","当一侧毗邻建筑物时，由毗邻建筑物处向另一方向施打",{"key":22,"text":23,"correct":24},"D","对基础标高不一的桩，宜先浅后深",false,{"key":26,"text":27,"correct":24},"E","对不同规格的桩，宜先小后大","ABC","本题考查的是钢筋混凝土预制桩基础施工技术。当基坑不大时，打桩应逐排打设或从中间开始分头向四周或两边进行；对于密集桩群，从中间开始分头向四周或两边对称施打；当一侧毗邻建筑物时，由毗邻建筑物处向另一方向施打；当基坑较大时，宜将基坑分为数段，然后在各段范围内分别施打，但打桩应避免自外向内或从周边向中间进行，以避免中间土体被挤密，桩难以打人；或虽勉强打入，但使邻桩侧移或上冒；对基础标高不一的桩，宜先深后浅；对不同规格的桩，宜先大后小、先长后短。这样可使土层挤密均匀，以防止位移或偏斜。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]