[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145575":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1145575,800,1,"单选题","（2020年真题）设有钢筋混凝土构造柱的抗震多层砖房，施工顺序正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","砌砖墙→绑扎钢筋→浇筑混凝土",false,{"key":16,"text":17,"correct":14},"B","绑扎钢筋→浇筑混凝土→砌砖墙",{"key":19,"text":20,"correct":21},"C","绑扎钢筋→砌砖墙→浇筑混凝土",true,{"key":23,"text":24,"correct":14},"D","浇筑混凝土→绑扎钢筋→砌砖墙","P113-118 设有钢筋混凝土构造柱的抗震多层砖房，应先绑扎钢筋，而后砌砖墙，最后浇筑混凝土。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]