[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145476":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1145476,800,2,"多选题","下列荷载中，属于可变荷载的有（ ）。（2013 年真题）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","雪荷载",true,{"key":16,"text":17,"correct":18},"B","结构自重",false,{"key":20,"text":21,"correct":18},"C","基础沉降",{"key":23,"text":24,"correct":14},"D","安装荷载",{"key":26,"text":27,"correct":14},"E","吊车荷载","ADE","本题考查的是可变荷载的定义。可变荷载也叫活荷载，是指在设计基准期内，其值随时间变化。如安装荷载、屋面与楼面活荷载、雪荷载、风荷载、吊车荷载、积灰荷载等。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]