[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145447":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1145447,800,2,"多选题","施工过程中，施工组织设计应进行修改或补充的情况有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程设计有重大修改",true,{"key":16,"text":17,"correct":14},"B","有关标准规范修订和废止",{"key":19,"text":20,"correct":21},"C","原审批人员发生变更",false,{"key":23,"text":24,"correct":14},"D","主要施工资源配置有重大调整",{"key":26,"text":27,"correct":14},"E","施工环境有重大改变","ABDE","2020教材P434 \u002F 2019教材P435 项目施工过程中，发生以下情况之一时，施工组织设计应及时进行修改或补充：1）工程设计有重大修改；2）有关法律、法规、规范和标准实施、修订和废止；3）主要施工方法有重大调整；4）主要施工资源配置有重大调整；5）施工环境有重大改变。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]