[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145363":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1145363,800,2,"多选题","外围护部品应完成的现场隐蔽项目验收有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","预埋件",true,{"key":16,"text":17,"correct":14},"B","与主体结构的连接节点",{"key":19,"text":20,"correct":21},"C","层间变形性能",false,{"key":23,"text":24,"correct":14},"D","变形缝及墙面转角处的构造节点",{"key":26,"text":27,"correct":14},"E","防火构造","ABDE","2020教材P409 \u002F 2019教材P410 1.外围护部品应完成下列隐蔽项目的现场验收：⑴预埋件。（2）与主体结构的连接节点。（3）与主体结构之间的封堵构造节点。（4）变形缝及墙面转角处的构造节点。（5）防雷装置。（6）防火构造。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]