[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145247":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1145247,800,1,"单选题","单位(子单位)工程的验收应由( )来组织。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位(项目)负责人",true,{"key":16,"text":17,"correct":18},"B","施工单位(项目)负责人",false,{"key":20,"text":21,"correct":18},"C","监理单位(项目)负责人",{"key":23,"text":24,"correct":18},"D","当地建设行政主管部门(项目)负责人","2020教材P353 \u002F 2019教材P354 单位工程质量验收组织与程序规定，建设单位收到工程竣工报告后，应由建设单位项目负责人组织监理、施工、设计、 勘察等单位项目负责人进行单位工程验收。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]