[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145243":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1145243,800,1,"单选题","分部工程的验收应由( )来组织。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目经理",false,{"key":16,"text":17,"correct":14},"B","项目总工程师",{"key":19,"text":20,"correct":14},"C","监理工程师",{"key":22,"text":23,"correct":24},"D","总监理工程师",true,"2020教材P348 \u002F 2019教材P349 分部工程应由总监理工程师(或建设单位项目负责人)组织施工单位项目负责人和项目技术负责人等进行验收。设计单位项目负责人和施工单位技术、质量部门负责人应参加主体结构、节能分部工程的验收;地基与基础分部工程还应有勘察单位项目负责人参加。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]