[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145226":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1145226,800,2,"多选题","成本核算的方法有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","制造成本法",true,{"key":16,"text":17,"correct":18},"B","综合成本法",false,{"key":20,"text":21,"correct":18},"C","期间成本法",{"key":23,"text":24,"correct":14},"D","完全成本法",{"key":26,"text":27,"correct":18},"E","直接成本法","AD","2020教材P323 \u002F 2019教材P324 成本核算中的制造成本法是指：首先是按照工程的人工、机械、材料及其他直接费（例如二次搬运费、工程点交、场地清理等核算出直接费用，再由项目层次的管理费等（例如临时设施摊销、管理薪酬、劳动保护费、工程保修、办公费、差旅费等）作为工程项目的间接费，而企业管理费用则属于期间费用，不计入施工成本中。除了制造成本法外，还有完全成本法，是指把企业生产经营发生的一切费用全部计算到产品成本之中。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]