[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145225":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1145225,800,1,"单选题","项目施工成本按“制造成本法”进行核算时，只计入施工项目成本的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","企业经营期间相关的费用",false,{"key":16,"text":17,"correct":18},"B","变动成本",true,{"key":20,"text":21,"correct":14},"C","企业总部的管理费",{"key":23,"text":24,"correct":14},"D","规费","2020教材P323 \u002F 2019教材P324 制造成本法与完全成本法的成本结转流程区别是：制造成本法把变动成本计人施工项目成本，把固定成本作为期间费用，完全成本法把变动成本和固定成本均计人施工项目成本",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]