[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145218":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1145218,800,1,"单选题","对某个项目的各项分部工程进行功能评分如下，计算得出相应各项的预算成本：从上表中数值看出，（ ）成本比重偏高，应做重点分析，寻求降低成本的措施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","主体结构工程",true,{"key":16,"text":17,"correct":18},"B","装饰装修工程",false,{"key":20,"text":21,"correct":18},"C","屋面工程",{"key":23,"text":24,"correct":18},"D","门窗工程","2020教材P326 \u002F 2019教材P328 价值系数=功能系数／成本系数；本题只需找出成本比重偏高的分部分项工程（即价值系数最低的项），并不需要精确计算，可用“功能评分／预算成本”进行估算。主体工程估算结果0.043、装饰装修工程估算结果0.064、屋面工程估算结果0.070、门窗工程估算结果0.078，由此可见，相对于单位功能评分值主体-工程的成本过高。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]