[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145215":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1145215,800,1,"单选题","挣值法主要是通过分析项目成本实施与（ ）之间的差异，从而判断项目实施费用、进度绩效的一种方法。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目进度目标期望",false,{"key":16,"text":17,"correct":14},"B","项目成本目标计划",{"key":19,"text":20,"correct":21},"C","项目成本目标期望",true,{"key":23,"text":24,"correct":14},"D","项目成本节约","2020教材P326 \u002F 2019教材P328 挣值法是通过分析项目成本目标实施与项目成本目标期望之间的差异，进而判断项目实施费用、进度绩效的一种方法。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]