[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145214":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1145214,800,1,"单选题","挣值法的三个成本值不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","已完成工作的预算成本",false,{"key":16,"text":17,"correct":14},"B","已完成工作的实际成本",{"key":19,"text":20,"correct":14},"C","计划完成工作的预算成本",{"key":22,"text":23,"correct":24},"D","计划完成工作的实际成本",true,"2020教材P326 \u002F 2019教材P328 挣值法主要运用三个成本值进行分析，它们分别是已完成工作预算成本、计划完成工作预算费用和已完成工作实际成本。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]