[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145213":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1145213,800,2,"多选题","用挣值法控制项目成本时，要运用到（ ）项的成本值进行分析。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","已完成工作的计划成本",false,{"key":16,"text":17,"correct":18},"B","已完成工作的预算成本",true,{"key":20,"text":21,"correct":18},"C","计划完成工作的预算成本",{"key":23,"text":24,"correct":14},"D","计划完成工作的实际成本",{"key":26,"text":27,"correct":18},"E","已完成工作的实际成本","BCE","2020教材P326 \u002F 2019教材P328 挣值法主要运用三个成本值进行分析，它们分别是已完成工作预算成本、计划完成工作预算费用和已完成工作实际成本。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]