[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145212":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1145212,800,1,"单选题","如果把进度偏差与投资偏差联系起来，则进度偏差可表示为（ ）与已完工程计划投资的差异。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","拟完工程计划投资",true,{"key":16,"text":17,"correct":18},"B","已完工程实际投资",false,{"key":20,"text":21,"correct":18},"C","未完工程计划投资",{"key":23,"text":24,"correct":18},"D","已完工程计划投资","2020教材P327 \u002F 2019教材P329 2.进度偏差SV=BCWP-BCWS;已完成工作预算成本为BCWP,计划完成工作预算成本，简称BCWS;",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]