[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145211":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1145211,800,1,"单选题","关于成本偏差CV的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","当CV为负值时，表示项目运行超出计划成本",false,{"key":16,"text":17,"correct":18},"B","当CV为负值时，表示项目运行超出预算成本",true,{"key":20,"text":21,"correct":14},"C","当CV为正值时，表示项目运行超出计划成本",{"key":23,"text":24,"correct":14},"D","当CV为正值时，表示项目运行超出预算成本","2020教材P327 \u002F 2019教材P329 当CV为负值时，即表示项目运行超出预算成本；当CV为正值时，表示项目运行节支,实际成本没有超出预算成本。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]