[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145210":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1145210,800,1,"单选题","关于进度绩效指数SPI的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","当SPI＜1时表示进度提前",false,{"key":16,"text":17,"correct":14},"B","当SPI＞1时表示进度延误",{"key":19,"text":20,"correct":14},"C","当SPI＜1时表示实际进度比计划进度快",{"key":22,"text":23,"correct":24},"D","当SPI＜1时表示实际进度比计划进度滞后",true,"2020教材P327 \u002F 2019教材P329 当SPI＜1时，表示进度延误，即实际进度比计划进度滞后；当时SPI＞1，表示进度提前，即实际进度比计划进度快。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]