[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145209":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1145209,800,2,"多选题","下列评估结果中，表示进度延误的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","进度绩效指数SPI＞1",false,{"key":16,"text":17,"correct":18},"B","进度绩效指数SPI＜1",true,{"key":20,"text":21,"correct":14},"C","成本绩效指数CPI＜1",{"key":23,"text":24,"correct":14},"D","进度偏差SV为正值",{"key":26,"text":27,"correct":18},"E","进度偏差SV为负值","BE","2020教材P327 \u002F 2019教材P329 当SV为负值时，表示进度延误，即实际进度落后于计划进度；当SV为正值时，表示进度提前，即实际进度快于计划进度。当SPI＜1时，表示进度延误，即实际进度比计划进度滞后；当SPI＞1时，表示进度提前，即实际进度比计划进度快。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]