[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145208":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1145208,800,1,"单选题","通常情况下，BCWS在整个工作实施过程应保持不变，但当（ ）时则会有变化。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","市场材料价格发生变化",false,{"key":16,"text":17,"correct":14},"B","市场人工费发生变化",{"key":19,"text":20,"correct":14},"C","项目措施项目发生变化",{"key":22,"text":23,"correct":24},"D","合同有变更",true,"2020教材P327 \u002F 2019教材P329 计划完成工作预算成本，简称BCWS即根据进度计划，在某一时刻应当完成的工作（或部分工作）以预算为标准计算所需要的成本总额，一般来说，除非合同有变更，在工作实施过程中应保持不变。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]