[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145203":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1145203,800,1,"单选题","下列工程项目条件中，不宜采用固定总价合同的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程施工周期比较短",false,{"key":16,"text":17,"correct":14},"B","设计图纸资料齐全",{"key":19,"text":20,"correct":21},"C","工程技术结构复杂",true,{"key":23,"text":24,"correct":14},"D","投标人投标准备期相对较长","2020教材P308 \u002F 2019教材P310 （2）总价合同。是指承建双方在合同约定时，将工程项目的总造价进行约定的合同。总价合同又分为固定总价合同和可调总价合同；固定总价合同适用于规模小、技术难度小、工期短（一般在一年之内）的工程项目。可调总价合同是指在固定总价合同的基础上，对在合同履行过程中因为法律、政策、市场等因素影响，对合同价款进行调整的合同；适用于工程规模大、技术难度大、图纸设计不完整、设计变更多，工期较长（一般在一年之上）的工程项目。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]