[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145202":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1145202,800,2,"多选题","宜采用成本加酬金合同的计价方式的建设工程项目有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","紧急抢修的工程项目",true,{"key":16,"text":17,"correct":14},"B","灾后重建的工程项目",{"key":19,"text":20,"correct":14},"C","新型项目",{"key":22,"text":23,"correct":14},"D","施工内容、经济指标不确定的工程项目",{"key":25,"text":26,"correct":27},"E","合同价格缺乏工程设计文件和施工技术管理条件的",false,"ABCD","2020教材P308 \u002F 2019教材P310 成本加酬金合同。合同价款包括成本和酬金两部分，双方在专用条款内约定成本构成和酬金的计算方法。适用于灾后重建、紧急抢修、新型项目或对施工内容、经济指标不确定的工程项目。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]