[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145201":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1145201,800,1,"单选题","实行工程量清单计价的工程，宜采用（ ）合同。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总价",false,{"key":16,"text":17,"correct":18},"B","单价",true,{"key":20,"text":21,"correct":14},"C","可调价",{"key":23,"text":24,"correct":14},"D","成本加酬金","2020教材P308 \u002F 2019教材P310 单价合同。是指承建双方在合同约定时，首先约定完成工程量清单工作内容的固定单价，或者在约定了固定单价的基础上，又在专用条款中约定了可以调整部分工程量清单单价的相关条款，其次是双方暂定或者核定工程量，然后核算出合同总价。工程项目竣工后根据实际工程量进行结算。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]