[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145198":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1145198,800,2,"多选题","因为分部分项工程量清单漏项或非承包人原因的工程变更而引起的措施项目发生变化，且造成了施工组织设计或施工方案变更，可调整的方式有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","原措施费中已有的措施项目，按原措施费的组价方法调整",true,{"key":16,"text":17,"correct":14},"B","原措施费中有类似的项目的，参考类似项组价方法调整",{"key":19,"text":20,"correct":21},"C","原措施费中没有的措施项目，由发包人根据措施项目变更情况，提出适当的措施变更，经双方确认后进行调整",false,{"key":23,"text":24,"correct":14},"D","原措施费中没有的措施项目，由承包人根据措施项目变更情况，提出适当的措施变更，发包人确认后进行调整",{"key":26,"text":27,"correct":21},"E","原措施费中没有的措施项目，由监理方根据措施项目变更情况，提出适当的措施变更，经发包方确认后进行调整","ABD","2020教材P309 \u002F 2019教材P311 对于已有相同和相似项目，应按相同和相似项目认定。已标价工程量清单中没有适用也没有类似变更工程项目，且工程造价管理机构发布的信息价格缺位的，由承包人根据变更工程资料、计量规则、计价办法和通过市场调査等取得有合法依据的市场价格提出变更工程项目的单价，报发包人确认后调整。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]