[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145197":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1145197,800,1,"单选题","承包人在施工中遇到暴雨袭击，导致工程停工，同时发生各项费用损失，按照不可抗力索赔处理原则，下列费用中发包人不予赔偿的是（ ），",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","被冲坏已施工的基础工程",false,{"key":16,"text":17,"correct":18},"B","停工期间设备闲置",true,{"key":20,"text":21,"correct":14},"C","清理现场，恢复施工",{"key":23,"text":24,"correct":14},"D","被冲坏的现场临时道路恢复","2020教材P311 \u002F 2019教材P313 10.不可抗力：因不可抗力事件导致的费用，发、承包双方应按以下原则分别承担并调整工程价款：1）工程本身的损害、因工程损害导致第三方人员伤亡和财产损失以及运至施工场地用于施工的材料和待安装的设备的损害，由发包人承担；2）发包人、承包人人员伤亡由其所在单位负责，并承担相应费用；3）承包人的施工机械设备损坏及停工损失，由承包人承担；4）停工期间，承包人应发包人要求留在施工场地的必要的管理人员及保卫人员的费用由发包人承担；5）工程所需清理、修复费用，由发包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]