[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145196":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1145196,800,1,"单选题","工程实施过程中出现不可抗力事件导致的费用，关于发、承包双方承担的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程修复费用由发包人承担，工程清理费用由承包人承担",true,{"key":16,"text":17,"correct":18},"B","发包人、承包人人员的伤亡由其所在单位负责，并承担相应费用",false,{"key":20,"text":21,"correct":18},"C","承包人的施工机械设备损坏及停工损失，由承包人承担",{"key":23,"text":24,"correct":18},"D","停工期间承包人应发包人要求留在施工现场的必要管理人员及保卫人员的费用，由发包人承担","2020教材P311 \u002F 2019教材P313 10.不可抗力：因不可抗力事件导致的费用，发、承包双方应按以下原则分别承担并调整工程价款：1）工程本身的损害、因工程损害导致第三方人员伤亡和财产损失以及运至施工场地用于施工的材料和待安装的设备的损害，由发包人承担；2）发包人、承包人人员伤亡由其所在单位负责，并承担相应费用；3）承包人的施工机械设备损坏及停工损失，由承包人承担；4）停工期间，承包人应发包人要求留在施工场地的必要的管理人员及保卫人员的费用由发包人承担；5）工程所需清理、修复费用，由发包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]