[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1145195":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1145195,800,1,"单选题","《建设工程施工合同（示范文本）》GF-2017-0201规定工程师在收到承包人送交的索赔报告的有关资料后，（ ）d未予答复或未对承包人作进一步要求，视为该项索赔被认可。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":21},"C","28",true,{"key":23,"text":24,"correct":14},"D","56","2020教材P312 \u002F 2019教材P314 发包人收到承包人的索赔通知书后，应及时查验承包人的记录和证明材料；发包人应在收到索赔通知书或有关索赔的进一步证明材料后的28d内，将索赔处理结果答复承包人，如果发包人逾期未做出答复，视为承包人索赔要求已经发包人认可。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]